The Law does not require any particular form, but it is advisable to send it in a way that proves the date of delivery and the content: registered post, or email to the address in the contract with confirmation of receipt.
Letter to the contractor about construction defects: what to write, and a letter generator
The right to demand repair of a construction defect is conditional on notice to the contractor: for a defect that could have been discovered on delivery, within one year of delivery, and for a latent defect, within a reasonable time of its discovery (Section 4A of the Sale (Apartments) Law). A written, detailed and dated notice is what will remain on file years later.
A defects letter to the contractor in a 30-second video

The video loads from YouTube only after you click. Go to the video page and transcript
In the video: This is Sidki. He grows when you wait. The right to demand a repair depends on notice to the contractor, and in a dispute you must prove when it was delivered and what it said. Write what the defect is, where, and when each one was discovered, and ask to schedule a repair. Send it by registered mail or by email with confirmation, and the site has a generator that produces the letter.
Contractor notice letter generator
Why in writing?
The Law does not prescribe a form for the notice, but in a dispute you must prove when it was given and what it said. An oral notice to a representative on site, or a conversation with the site manager, is not a notice that can be proved two years later. A dated letter setting out the defects solves the problem.
The notice has a further function: under section 4B(b), the two years within which it is examined whether a defect has recurred after repair are counted from the date of the notice. Without a documented notice date, it is difficult to exercise the right to repair at the contractor's expense.
What should the notice include?
In the notice, state the details of the purchaser and the apartment and the date of delivery, a specific list of the defects (what, where and when each one was discovered), photographs, a request to schedule a date for repair under section 4B(a), and contact details for scheduling, with a reservation of rights.
- Details of the purchaser and the apartment, and the date of delivery.
- A list of the defects: what, where, and when each one was discovered. As specific as possible.
- Photographs, as an appendix or a link.
- A request to schedule a date for repair, in order to give the contractor the reasonable opportunity to repair that the Law requires (section 4B(a)).
- Contact details for scheduling, and a reservation of rights.
To whom to send it, and how
To the company that sold you the apartment, that is, the seller under the contract, even if the construction was carried out by another contractor. Check the contract for the address to which notices must be sent. Send it in a way that leaves proof: registered post, or email to the address in the contract with confirmation of receipt, and keep a copy.
What happens after the letter?
Allow the contractor to come and repair and document every visit, and do not sign a "completion of repairs" form or a waiver without checking. If the contractor does not respond or the defect recurs, this is the time for an engineer's expert opinion and a demand letter from a lawyer before suing.
- Allow the contractor to come and repair, and document every visit: the date, what was done, and what remains.
- Do not sign a "completion of repairs" form or a waiver without checking. Under section 7A(a) of the Law the provisions of the Law may not be contracted out of except in the purchaser's favour, but signing such a confirmation may complicate proof later on.
- If the contractor does not respond, or the defect recurs, this is the time for an engineer's expert opinion and a demand letter from a lawyer before suing. This is discussed in the article Demand letter before a lawsuit.
When is it better for the letter to come from a lawyer?
When the defects are numerous or material, when the inspection period for an important item is about to expire, when the contractor has already rejected the demand, or when the residents' committee is acting on behalf of the whole building. In such situations the letter is part of building the case, and it is worth drafting it together with the expert opinion.
Is oral notice enough?
The law does not prescribe a form of notice, but the burden of proof lies on the buyer, and oral notice is very weak as evidence. We therefore do not recommend relying on it; send orderly written notice, in a way that leaves confirmation of delivery.
The law does not prescribe a form of notice. In CA 8939/01 Avitzur v. Heftziba (2 September 2003), the Supreme Court held that even a contract clause requiring registered mail does not defeat a buyer who gave notice another way. But the same judgment stressed that the advantage of written notice, and registered mail in particular, is that it documents the notice, its date and its content, and that the burden of proof lies on the buyer. A buyer's bare statement that they notified the contractor orally is not enough. The buyers in that case succeeded only because the contractor itself had tried to repair the defects, which proved it knew of them.
The practical conclusion: oral notice is very weak as evidence, and we do not recommend relying on it. A conversation with the site manager or a customer service representative is no substitute for orderly written notice sent in a way that leaves proof of delivery.
A "transparent" defect: visible, but not to the buyer
A deviation from the building regulations that an ordinary buyer cannot identify by visual inspection, such as a room smaller than the minimum area, may be treated as a hidden nonconformity, for which notice is given within a reasonable time of discovery. Even so, do not rely on this: send written notice immediately, and in any event before the end of the first year.
The distinction between a defect discoverable at delivery (notice within one year) and one not discoverable by reasonable inspection (notice within a reasonable time from discovery) is judged by the ordinary buyer. In CC (Central District) 2270-08-07 Diba v. Plassim (11 May 2010), the Court held that the required inspection is a visual one by a layperson, and that a deviation from the building regulations that cannot be identified without knowing them, such as a room smaller than the minimum area or width, is a "transparent" nonconformity treated as hidden. The Court relied on CA 8949/07 Ahim Ezra v. Zeev: having seen the apartment before buying does not exempt the seller, unless it drew the buyer's attention to the standard and the deviation.
An engineer's opinion sent to the contractor within a reasonable time of receiving it may also serve as notice of defects that could not be identified earlier (LCA 2988/11 Shikun Ovdim v. Zakai, 4 July 2011, para. 15).
Still, it is better not to rely on this distinction. What you see at delivery goes into the delivery protocol, and what is discovered later is sent in writing at once, and in any case before the end of the first year.
Case law and sources
- Sale (Apartments) Law, 5733-1973: sections 4A, 4B, 7A.
- CA 8939/01 Avitzur v. Heftziba Construction Ltd. (2 September 2003), paras. 5-7.
- CC (Central District) 2270-08-07 Diba v. Plassim Development and Construction Ltd. (11 May 2010).
- LCA 2988/11 Shikun Ovdim Ltd. v. Zakai (4 July 2011), para. 15.
The judgments were read in full and the texts checked against the sources on 23 October 2026. This is general information and not advice on a specific matter.
About the author
Amos Ilan, Advocate, is a lawyer (Bar No. 35320) and a notary (licence 214444). The office is at 17 Tzahal Street, Nes Ziona, and handles real estate transactions, construction defects, condominium disputes and civil litigation. Alongside his legal work he has practical knowledge, not based on formal training, of engineering, appraisal and electrical and building systems, and he personally conducts the cross-examination of experts in construction defects cases.
Questions and answers
Is it mandatory to send a registered letter?
The contractor is not answering. How long should I wait?
The Law requires that the contractor be given a reasonable opportunity to repair, and obliges him to repair within a reasonable time. Where there is no response, it is advisable to send a written reminder and to take advice, especially as deadlines approach.
Does the generator save my details?
No. The generator runs in the browser only, and the details are not sent to the website or to any other party, and are not stored.
Need a lawyer or a notary?
A short initial consultation call, to understand whether and how we can help.